| The Group Rover Alcisa wide the entrance vestibule of the Hig Speed Train in Madrid |
|
The Group Rover Alcisa, across his companies Rover Alcisa Construcción and Iberovías, is going to construct the platform for a double route of 220 Km/h High Speed, between Atocha and Torrejón de Velasco.
The knowledge and Rover Alcisa's experience construction in the railway infrastructures and Iberovías's powerful and modern machinery, Rover Alcisa allows the Group the construction in UTE between both companies of a platform for the extension from two to four routes in Alta Velocidad's lines between Madrid, Atocha's station, and Torrejón de Velasco.
The actions object of this project can divide in two differentiated parts: Section Pinto-Torrejón de Velasco and a new parking of surroundings.
Section Pinto-Torrejón de Velasco The section includes a jump of routes in the P.K. 305+200 (P.K. 26+000 of the L.A.V. of Sevilla), to define a quadruple route, with the new routes attached to those of the L.A.V. Madrid - Sevilla for both margins, up to the connection with the following section: Torrejón de Velasco-Seseña, nowadays in works.
For the accomplishment of the jump of routes, the double-wide track separates in two only routes in the P.K. 304+315. The double route has a total length of 4.315 m, up to the P.K. 304+315. The only(unique) route felt Madrid has a length of 2.644 m, and the only route felt The Levant, 2.202 m. The section understands(includes) the following significant works: - Structures pergola of 252 m on the L.A.V. Madrid - Seville, of the P.K. 305+073 to the P.K. 305+325. - Step under the M-506 for a portico formed by screens of piles, of 24 m of length, in the P.K. 300+520. - 1 top Step of the branch of the link of the M-506 with the R-4 in the P.K. 300+550. - 2 top Steps for reinstatement of ways. - 1 Underpass by means of a frame pushed under the L.A.V. Madrid - Sevilla. In addition it includes the transverse drainage by means of frames of reinforced concrete and pipes, 3 of them pushed under the L.A.V. Madrid - Seville, and the longitudinal drainage, the reinstatement of road affected and ways for access to estates, the civil work of the railway facilities and the execution and later restoration of two lendings for (training) of terraces.
New parking of suburban train The current parking of the line of surroundings C-4, placed in Parla Industrial's station, will be affected by the works of this project, being foreseen the raising of the same one and his reinstatement in the own line C-4 by means of a parking assistant. Parla Industrial will still have the new parking placed between and the lay-by of Butane and the current bifurcation. His principal characteristics are the following ones: - Has 3 routes electrified with useful length top to 410 m. - The route is of Iberian width trained for naughty polyvalent monoblock (PR-01) with rail UIC-54 in long welded bar, on balasto. - The devices of routes are of the type P, with tangent 0,11 in the detours located in the parking and 0,09 for the detours and leaks that are included in the general route. - The electrification will realize with chain type ADIF CA-160 in direct current. A feeder of assault will be executed from the existing substation in Parla Industrial. - New electronic parking with aptitude to include in the same blockade and the remote control. - Technical building to lodge the equipments, including the office of traffic. |